To: Captain Jack Casey, Director of
Operations Battleship Cove
Cc: Paula Hague
Ken Preble
Volunteer Crew DD-850
Subj: May 2006 Spring Field Day
Despite
adverse weather conditions at times, the Volunteer Crew of the KENNEDY was
still able to maintain a high degree of job completion. The unscheduled
priority of the weekend was to make repairs to the decks on both Port and
Starboard side of the -01 level just forward of the ASROC Launcher. We
believe we have secured what may have been a major source of water leaking into
the ship.
However, even with a dedicated group working on that, there
was still much done through out the ship. From the Engineering spaces to the
Bridge, to the main deck to DASH, all about.
I fear though, that I will not capture everything that was
done, but sincerely hope that I capture a majority of the work.
I will provide listing of those attending under separate
cover but the total number in attendance was sixty-one. A pretty solid crew I
would offer to you.
Below is a summary of what was accomplished.
Welded
patch on deck - over Fan Room, Paint locker, Laundry area Starboard side
01 level under ladder leading to -02 level.
Welded
patch over deck Port side -01 level under ladder leading to -02 level.
Cleaned
and primed both areas for painting.
Cleaned
and primed locations along stardboard side from waterline to main deck
in preparation for painting
Replaced
the main throttle wheel and cruising turbine wheel with rope braided
throttle wheels
Initiated
dusting/cleaning in B4
Mounted
Gauges on SSTG in B4
Polished
Brass throughout B4
Installed
copper sensing lines to various gauges on Evap in B4
Moved
excess Lube Oil Purifier parts to B2
Began
cleaning Condensat Discharge line Removing paint, polishing, etc.
Replaced
missing valve behind Salinity Indicator in B4 from replacement acquired
from B2.
Removed
un-necessary angle iron brackets from top of Throttle Board in B4
Installed
brass knob on Engine Order Telegraph B4.
Installed
numerous missing valve handwheels B4
Painted
Salinity Indicator B4
Mounted
Conductivity meter B4
Removed
paint from Throttle Wheels B4
Installed
CO2 Hose funnel to hose by workbench Port side B4
Removed
Rope from behind Evap in B4
Secured
440V Power Panel 2-141-2 in B4
Removed
plexiglass from below Throttle Wheels in B4
Worked
on numerous light fixtures including bulb and starter replacement in B4
including lower level.
Unseized
all throttle controls in B4.
Installed
grease fittings and greased throttle linkages in B4.
Replaced
missing gauge glasses on Throttle Board in B4
Began
prep, prime and painting of Aft Diesel
Began
prep and priming of Boat winch on fantail
Began
working on prepping ASROC Loader Crane for painting.
Removed
countless number of rusted clamps from around Gooseneck vents throughout
ship, prepped and primed for painting.
Removed
rusted clamp clean, primed and reinstalled around voice tube on PortBridge
Wing.
Open
covers, carefully cleaned out dirt and debri from Aft Expansion
joint.
Removed
rusted sign from ASROC Launcher Prepped, Primed and painted.
Removed
clamp from Gooseneck vent by ships bell prepped, primed and painted.
Removed
Battle
Ribbons from bridge face for restoration.
Removed
all pallets, old frames, debris from DASH Hanger
Provide
Duty Electrician as required.
Replaced
all light bulbs in DASH Hangar.
Mounted
wake light and connected into existing lighting.
Continued
restoration work on 21MC
Continued
to work on tracing and restoring Sound Powered Phone System.
Continued
to work on replacing light fixtures in B4 Lower level.
Added
Navy type receptacle in DASH Hanger Starboard side By Rollup door.
Energized
Aft Diesel
Energized
Anchor Windlass
Installed
Carbon pile regulator on Starboard bulkhead in IC Gyro
Installed
and painted protective cage around Carbon Pile Regulator
Converted
Navy style plugs to 3-prong plugs with 3 cords.
Fabricated
2 Sound Powered Handsets from the salvaged parts available.
Fabricated
4 Sound Powered Headsets from salvaged parts and mounted them on the IC
Room bulkheads for display.
Removed
old telephone wiring and replaced with armor cable on the NavigationBridge
Weather Deck 1MC speaker at frame 58C/L.
Installed
armor cable to the 1MC speaker located on the Helicopter Platform at frame
145P and tied into ship's wiring.
The
1MC Speaker Project is now complete as far as we can go at this time with
all speakers working.
Conducted
IC Room Tour for BBCove Guests.
Removed
IC Room clock for cleaning and lubrication.
Painted
all armor cable installed on the weather deck last winter for the 1MC
speakers and the X40J SP circuits.
Painted
Cargo lights for mounting on Bridge
Removed
pelorus Port side Bridge (Safety Hazard)
Began
restoration of windows on ASROC Control Station
Provide
tours to Scout Troops of Bridge, IC Gyro, Dash, Focsle, Radio and
Engineering Spaces.
Large
correct size bulletin board installed outside ship office.
Deck
taken up, brushed, and primed in emergency radio awaiting installation and
mounting of DASH electronic equipment
MT
53 Handling room shell and powder racks 1/3 prepped and painted correct
scheme, another 1/3 prepped awaiting painting
New
scuttle installed on FWD hatch on focsle to replace rotted one.
Mt
51 needle gunned top and all sides including both hot shell doors as well
as primed. Two by Two section on bottom of mount needled and
primed. Needs to continue. Note: Found training alarm to be
missing from bottom of MT 51. Need to get from store room and
install once bottom of mount is painted.
Mt
51 barrels lowered for prepping and removing all old caulking . Gun
resealed to keep out water. Recommended that NO ONE raise or try to
move barrels of gun or will break seal.
Grinding,
prepping, and priming of focsle area to FWD deckhouse bulkhead.
Attempted
to remove optic doors on MT 51 to no avail as of yet. Inspected and
found all doors to be rotted and in serious disrepair. New ones need
to be fabricated for MT 51 and MT 53.
Needled,
primed, and sealed Gun Captains Hatch on top of mount. Note that the
hatch was in serious disrepair.
Believed
to have stopped water leak into Sonar and radio by sealing with caulk the
SPS-29 Radar wave guide that comes down from mast, through signal bridge,
into sonar, and finally into radio. This needs to be monitored.
Crawled
under In-port Navigation station on signal bridge and sealed up wire way
that was leaking into Bridge. Needs to be inspected randomly.
One
bridge window totally removed, primed and wire wheeled frame and
structural frame. Window was sealed.
Sliding
Plexi-glass doors were made for stbd side bookcase in mess decks
5
boxes of nautical charts were sorted
Manuals
in Engineering office were sorted and logged by category and ship class
Fanfare
bitter ends were spliced and then connected with black electrical tape.
Repaired
leaking fitting on maindeck starboard side that was leaking into B1.
Cleaned,
Prepared and Primed bolts on deck around forward expansion joint
Correct
drain sink installed in Oil King Shack to complete this exhibit. (Cosmetic
restoration only).
Prepared
and served delicious and mouth watering meals from Wednesday 5/17 to
Sunday 5/21
Distributed
Volunteer Crew shirts to all Volunteers.
The Volunteer Crew will return the weekend of
June 16-18th to continue the restoration / preservation effort.
As always with so much accomplished it is
not my intention to overlook the great work completed by our Volunteers. For
those tasks I have over looked my apologies. Ed, Rich and I will continue to
work on a better manner to collect and record the wide variety of work done by
a great crew.
Included in this weekend, were seven first
timers and several that have not been aboard for some time but have returned
and contribute as always.
In addition to the work accomplished, the new
friendships created and the comradeship of the crew we also collected $400
which will be used to purchase and ship items to our shipmates and soldiers
serving in Iraq . This is the second Field Day in a row we have done this and we
will continue to do this until all of our troops are safely home.
So there be any questions feel free to contact
me.